Problem Statement
Before production cutover, the AWS deployment needs objective proof that it can
handle expected load, meet security requirements, and be operated or rolled back
safely.
Scope
In scope:
- Performance validation
- Security review and findings triage
- Runbooks and operating guidance
- Rollback proof and go or no-go sign-off
Out of scope:
- New platform capabilities beyond readiness validation
- Multi-region disaster recovery program
- Post-launch optimization work
Technical Approach
- Use the existing benchmark tooling for representative load tests.
- Validate alerting, rollback, and runbooks in a controlled environment.
- Record a go or no-go decision with explicit residual risks.
Dependencies
Hard dependencies:
- Data layer
- Compute layer
- Networking layer
- Observability layer
- CI/CD pipeline
Role in tree:
- Final gate for this epic
Acceptance Criteria
Proposed Definition Of Done
Validation Plan
- Run benchmark scenarios that represent expected production traffic.
- Record latency, throughput, cache, and error-rate results.
- Review IAM, secrets, encryption, and network controls.
- Trigger at least one test alarm and verify notification and recovery.
- Execute rollback in a non-production environment.
- Record the final go or no-go decision with owners.
Numeric Exit Thresholds
- p95 latency target: document in this issue before execution starts
- Error-rate target: document in this issue before execution starts
- Throughput target: document in this issue before execution starts
- Open findings at sign-off: Critical = 0, High = 0 unless waived explicitly
Risks And Mitigations
- Risk: acceptable performance remains subjective.
- Mitigation: Fill in the numeric thresholds before execution begins.
- Risk: runbooks exist but are not operationally useful.
- Mitigation: Require review sign-off and one rollback rehearsal.
Handoff Notes
This issue is the epic close gate. If any threshold or sign-off item is missing,
the epic remains open.
AC/DoD Coverage Matrix
| Item |
Type (AC/DoD/Non-goal) |
Status (Met/Partial/Unmet/Unverified) |
Evidence (spec/tests/behavior) |
Notes |
| Load test shows acceptable performance |
AC |
Unverified |
Benchmark report |
Source AC |
| Security review has no critical findings |
AC |
Unverified |
Security review |
Source AC |
| All runbooks created and reviewed |
AC |
Unverified |
Runbook index |
Source AC |
| Go-live checklist fully complete |
AC |
Unverified |
Final checklist |
Source AC |
| Production deployment successful |
AC |
Unverified |
Go-live evidence |
Source AC |
| Benchmark report with p50, p95, p99, throughput, and error rate is attached. |
DoD |
Unverified |
Issue evidence |
Proposed DoD |
| Security findings summary and disposition are attached. |
DoD |
Unverified |
Issue evidence |
Proposed DoD |
| Runbook index and review sign-off are attached. |
DoD |
Unverified |
Issue evidence |
Proposed DoD |
| Rollback test evidence and final go or no-go record are attached. |
DoD |
Unverified |
Issue evidence |
Proposed DoD |
Problem Statement
Before production cutover, the AWS deployment needs objective proof that it can
handle expected load, meet security requirements, and be operated or rolled back
safely.
Scope
In scope:
Out of scope:
Technical Approach
Dependencies
Hard dependencies:
Role in tree:
Acceptance Criteria
Proposed Definition Of Done
Validation Plan
Numeric Exit Thresholds
Risks And Mitigations
Handoff Notes
This issue is the epic close gate. If any threshold or sign-off item is missing,
the epic remains open.
AC/DoD Coverage Matrix